Aripa Arquitectos

projects - hospitals

Centro Hospitalar e Universitário de Coimbra

Client: Centro Hospitalar e Universitário de Coimbra
P.O.: Centro Hospitalar e Universitário de Coimbra
Gross area: 2 700 m2
Estimate: 6 000 000 €

Hospital Central da Madeira

Client: Governo Regional da Madeira
P.O.: Secretaria Regional dos Assuntos Parlamentares e Europeus
Gross area: 175 000 m2
Estimate: 239 000 000 €
Start date: 2016

Hospital Central da Madeira

Hospital de S. João - Ala Pediátrica

Client: Centro Hospitalar de S. João
P.O.: Centro Hospitalar de S. João
Gross area: 15 000 m2
Estimate: 25 000 000 €

Hospital Divino Espírito Santo de Ponta Delgada

Client: Hospital Divino Espírito Santo de Ponta Delgada
P.O.: Hospital Divino Espírito Santo de Ponta Delgada
Gross area: 4 500 m2
Estimate: 3 600 000 €

IPO Coimbra

Client: IPO COimbra
P.O.: IPO Coimbra
Gross area: 18 125 m2
Estimate: 20 659 000 €

IPO Coimbra

Hospital das Forças Armadas - Edificio H05

Client: Ministério da Defesa
P.O.: Estado Maior Forças Armadas
Gross area: 3 100 m2
Estimate: 7 500 000 €

Orthopedic Hospital Sant'ana

Expansion of Hospital Sant'ana - Parede, Portugal

Client: Santa Casa da Misericórdia de Lisboa
P.O.: Santa Casa da Misericórdia de Lisboa
Gross area: 6 800 m2
Estimate: 11 000 000 €
Start date: 2014
Phase: Competition

3D: 1825 Empreiteiros Digitais

Orthopedic Hospital Sant'ana

Luanda's Hospital - Angola

University Hospital of Luanda

Client: Banco Privado Atlantico / Universidade Navarra
Gross area: 88 000 m2
Estimate: 206 000 000 €
Start date: 2014
Phase: Competition

3D: 1825 Empreiteiros Digitais

Luanda's Hospital - Angola

Center Anti Cancer Constantine

Center Anti Cancer in Constantine Algeria

Client: Defesa Nacional da Republica da Argélia
P.O.: Defesa Nacional da Republica da Argélia
Gross area: 25 000 m2
Estimate: 60 000 000 €
Start date: 2014
Phase: Competition

3D: 1825 Empreiteiros Digitais

Center Anti Cancer Constantine

Massinga - Mozambique

Hospital of Massinga

Client: Ministério da Saúde MISAU - República de Moçambique
Gross area: 8 000 m2
Estimate: 12 000 000 €
Start date: 2014
Phase: Competition

Programming, Renovation and Expansion

Massinga - Mozambique

Sousa Martins |Guarda|

Hospital of Sousa Martins

Client: M. da Saúde / ARS do Centro
P.O.: Unidade Local de Saúde da Guarda EPE
Gross area: 77 850 m2
Estimate: 80 000 000 €
Start date: 2008
Phase: Work Complete 2014
Classification: Winner of the Competition

Model: Norigem
Photography: Ricardo Gonçalves, José Campos

Refurbishment and Extension

Sousa Martins |Guarda|

Douera - Algeria

University Hospital of Douera

Gross area: 41 500 m2
Estimate: 60 000 000 €
Start date: 2013
Phase: Competition

3D: 1825 Empreiteiros Digitais

Douera - Algeria

Bechar - Algeria

University Hospital of Bechar

Gross area: 60 000 m2
Estimate: 90 000 000 €
Start date: 2013
Phase: Competition

3D: 1825 Empreiteiros Digitais

Bechar - Algeria

Angra do Heroísmo |Azores|

Hospital of Santo Espírito da Ilha Terceira

Client: Mota Engil/Somague/Marques/Dalkia
P.O.: Reg. Autonoma dos Açores / SRS
Gross area: 49 163 m2
Estimate: 61 700 000 €
Start date: 2009
Phase: Work complete 2012
Classification: Winner of the Competition

Photography: José Campos

Lamego |Viseu|

Hospital of Proximity of Lamego

Client: Min. Saúde / ACSS /CHTMAD
P.O.: C.H.T.M. e Alto Douro
Gross area: 18 000 m2
Estimate: 24 000 000 €
Start date: 2007
Phase: Work complete 2013
Classification: Winner of the Competition

Model: Aripa
Photography: Ricardo Gonçalves, José Campos

Lamego |Viseu|

Seixal |Setubal|

New Hospital of Seixal

Client: M. da Saúde / Hospital Garcia de Orta
Gross area: 31 520 m2
Estimate: 36 800 000 €
Start date: 2010
Phase: Competition
Classification: Winner of the Competition

3D: Ideias e Design
Model: Aripa
Photography: Aripa

Seixal |Setubal|

São João |Porto|

Centro Hospitalar de S.João e Valongo EPE

Client: Centro Hospitalar de São João EPE
Start date: 2010
Phase: Work in Progress
Classification: Winner of the Competition

Barcelos |Braga|

New Hospital of Barcelos

Client: M. da Saúde / ARS do Norte
Gross area: 50 000 m2
Estimate: 50 000 000 €
Start date: 2010
Phase: Prior Study (under consideration by the promoter)
Classification: Winner of Competition

3D: Ideias e Design
Model: Aripa
Photography: Aripa

Barcelos |Braga|

Cascais |Lisboa|

HPP Hospital de Cascais Dr. José de Almeida

Client: CGD-HPP/Teixeira Duarte
P.O.: Ministério da Saúde
Gross area: 46 000 m2
Estimate: 64 700 000 €
Start date: 2007
Phase: Work completed in 2009
Classification: Winner of the Competition

Photography: Ricardo Gonçalves

Cascais |Lisboa|

Hospital de Todos os Santos |Lisboa|

Client: Mota Engil / Opway / Casais / Efacec
P.O.: Ministério da Saúde / ACSS
Gross area: 230 000 m2
Estimate: 350 000 000 €
Start date: 2009
Phase: Competition
Classification: Not Awarded

Hospital de Todos os Santos |Lisboa|

Hospital of Évora

Client: M.S. / Hospital de Espírito Santo de Évora
P.O.: M.S. / Hospital de Espírito Santo de Évora
Gross area: 90 000 m2
Estimate: 98 000 000 €
Start date: 2009
Phase: Competition
Classification: Not Awarded

Teder with pre-qualification

Infante D. Pedro |Aveiro|

Hospital Infante D. Pedro

Client: M.S. / Constructora San José SA. EPE
P.O.: M.S. / Hospital Infante D. Pedo EPE
Gross area: 3 200 m2
Estimate: 1 900 000 €
Start date: 2005
Phase: Work completed in 2007
Classification: Winner of the Competition

Service: Emergency

Infante D. Pedro |Aveiro|

Seia |Guarda|

Hospital Nossa Senhora da Assunção

Client: M. da Saúde / ARS do Centro
P.O.: M. da Saúde / ARS do Centro
Gross area: 6 116 m2
Estimate: 5 820 000 €
Start date: 2004-2008
Phase: Work completed in 2008
Classification: Winner of the Competition

Caldas da Rainha |Leiria|

Center Hospital of Caldas da Rainha

Gross area: 21 970 m2
Estimate: 15 000 000 €
Start date: 2001
Phase: Projecto base 2003
Classification: Winner of the Competition

Expansion and Renovation

Functional reform program for installation of the West North Central Hospital in 2011

Caldas da Rainha |Leiria|

Póvoa de Varzim |Vila do Conde|

Centro Hospitalar de Póvoa de Varzim

Client: Ministério da Saúde / DGIES
P.O.: Ministério da Saúde / DGIES
Gross area: 24 415 m2
Estimate: 20 000 000 €
Start date: 2002
Phase: Prior Study
Classification: Winner of the Competition

Reform program in 2011

Vila Franca de Xira Hospital

Client: Grupo CGD, HHP/Teixeira Duarte
P.O.: Min. da Saúde / ACSS
Gross area: 75 733 m2
Estimate: 66 600 000 €
Start date: 2006
Phase: Competition
Classification: Not awarded

Vila Franca de Xira Hospital

Braga University Hospital

Client: Grupo CGD, HHP/Teixeira Duarte
P.O.: Grupo CGD, HHP/Teixeira Duarte
Gross area: 123 500 m2
Estimate: 110 000 000 €
Start date: 2005
Phase: Competition
Classification: Not awarded

Braga University Hospital

S. Sebastião |Santa Maria da Feira|

Centro Hospitalar de Entre o Douro e Vouga EPE

Client: S. Costa / Engil / Mota e Cª, ACE
P.O.: Ministério da Saúde / DGIES
Gross area: 48 500 m2
Estimate: 48 500 000 €
Start date: 1992
Phase: Work completed in 1998
Classification: Winner of the Competition

Tomar |Santarém|

Hospital Nossa Senhora da Graça

Client: Soares da Costa / Engil ACE
P.O.: Ministério da Saúde / DGIES
Gross area: 41 000 m2
Estimate: 41 000 000 €
Start date: 1993
Phase: Work completed in 2002
Classification: Winner of the Competition

Vale de Sousa |Penafiel|

Hospital Padre Américo

Client: Engil/S. Costa/Mota e Cª ACE
P.O.: Ministerio da Saúde/DGIES
Gross area: 52 000 m2
Estimate: 52 000 000 €
Start date: 1999
Phase: Work completed in 2002
Classification: Winner of Competition

Vale de Sousa |Penafiel|

Ponta Delgada |Açores|

Hospital do Divino Espírito Santo de Ponta Delgada EPE

Client: Engil / Marques, ACE
P.O.: RAA/Secretaria Regional da Saúde
Gross area: 54 500 m2
Estimate: 65 400 000 €
Start date: 1989
Phase: Work completed in 1998
Classification: Winner of the Competition